Keokuk Street Plan Could Speed Up

Keokuk, IA – Keokuk could speed up its multi-year, multi-million dollar street repair program.

Initially, the city council decided to borrow $12,000,000 over 12 years to put in new concrete streets.

Now, the streets sub-committee has come up with a proposal that calls for the money to be borrowed over four years.

Chairman Gary Stepp says the first few projects have shown him that future construction could take place sooner rather than later.

He says the impact of the new plan on Keokuk's property tax rate will determine if it gains council approval.

The proposal includes money to replace Grand Avenue over the next two years.

You can hear more from Streets Sub-Committee Chairman Gary Stepp by clicking the audio link above.

Additional Information
* One project, High Street from 13th to 17th Streets has been completed.
* Pioneer Lane/Brookshire Drive and Timberline Drive are currently being worked on.
* South 14th from Ridge to 16th, North 16th from Main to Morgan, and Concert from 16th to 18th are scheduled to be completed by late fall.

Stepp's plan for 2008 through 2010.
* Phase 2 - 2008
South 2nd from Bank to Carroll
Concert from 10th to 16th
North 15th from Fulton to Orleans
Belknap from Main to Kilbourne
Lower Grand Avenue.

* Phase 3 - 2009
Upper Grand Avenue
South 5th from Exchange to Palean
Pleasant Lane
South 17th from Main to Ridge
South 19th from Main to Timea

* Phase 4 - 2010
South Oak
North Oak
Indian Hills

Total Cost - $12,000,000+
Total Blocks - 52
Total Intersections - 37